Update: Construction of the streetcar work will begin in the Pearl District on Lovejoy. Here we go folks, try to be safe and avoid this area during rush hour time.

Please be advised that installation of a sewer line will begin the week of Feb. 22, 2010 on NW 9th and Lovejoy. This work area will be under construction for up to nine weeks.
(Construction subject to change).

  • 9th Ave will be restricted to 1 northbound lane.
  • 2-way traffic will be maintained on Lovejoy.
  • 9th Ave will be closed to southbound bicycle traffic.
  • Streetcar Loop construction will begin soon in the Pearl District. Work below occurs in 2010:

  • Sewer Feb 22 – May 2
  • Water Work May 3 – July 2
  • Track Construction Sept 6 – Oct 31
  • A 2-Week Streetcar closure will occur Sept 13 – 26
  • The Broadway Bridge will be closed July 5 – Sept 5
  • Construction subject to change.
  • Lane closures and detours will occur during this time. Pedestrians and driveways will be accommodated. Thank you all for your patience.