Track installation and utility work on the Lovejoy ramp thru 9th & Lovejoy intersection Weeks of Aug 9, Aug 16, Aug 23
NW Lovejoy ramp to the bridge will be closed east of 9th for this work.
Beginning July 28 the track construction will cross 9th Ave on Lovejoy closing the intersection.
Driveway access will be accommodated.
Sidewalks to remain open.
Sewer work from Lovejoy to Marshall on 9th Week of Aug 16
Lanes may be closed at each intersection to facilitate the installation of the lining
This work may result in a chemical-like odor in the surrounding area and will require the use of a compressor.
OCS and Traffic Signal Foundation/Conduit installation 11th/10th/9th & Lovejoy
Weeks of Aug 9, Aug 16, Aug 23
Expect intermittent lane closures.
The weeks of Aug 9 and Aug 16 the work hours will be between 7:00 AM and 4:00PM
Work will occur at night the week of Aug 23. Work hours will be from 11:30PM to 5:30AM.